End User: TAWZEA
Contractor: ACCIONA AGUA
Status: Completed
- Testing, commissioning and Energization of 2 Transformers 13.8 / 0,69 kV
2500 kVA Primary: Delta Secondary: Star.
- 3150 kVA Primary: Delta Secondary: Star.
- Testing, commissioning and Energization of 2 Transformer 13.8/ 0,38 kV
2000 kVA Primary: Delta Secondary: Star.