The 220/66/22 kV Madenty II Substation project was executed by IGEC for the client SIEYAN, with the end user being EETC.
The project involved testing and commissioning of electrical equipment for the substation, including 220kV and 66kV GIS LCC, interface and interlocking, control and protection panels testing and commissioning, 11kV switchgear testing and commissioning, and all outdoor components such as surge arrestors, line traps, CCVT, neutral DS, and NER. The project also included testing of 175 MVA and 40 MVA transformers, including TRMK and MDU. IGEC’s team of experts worked diligently to ensure that all equipment was properly tested and commissioned, in accordance with industry standards and the client’s specifications. The successful completion of this project demonstrates IGEC’s expertise in substation design, engineering, construction, and maintenance, and their commitment to delivering high-quality services to their clients
Project Facts and Figures
End User | EETC |
Main contractor | SIEYAN |
Testing and Commissioning 220kV/66kV/22kV substation electrical equipment including but not limited to,