MYDP RAS AL KHAIR

Aug 22, 2025 2 mins read

End User: ARAMCO 
Contractor: EATON 
Status: Completed
- 13.8 KV MV SWG
- Point to point (scheme check)
- C.B testing
- Bus bar testing
- Relay acceptance test (REF 615 & REF 620 for ATS)
- Protection Relay final setting applying
- Power meter testing
- CT & VT testing
- Functional test
- Auxiliary relay testing
- Modular Substation
- RMU testing (bus bar IR – CR – HI POT – relay testing and final setting
(P3U30) – CT testing – C.B testing)
- Dry Type Transformer (TTR – Winding Resistance – IR & PI)
- MDP LV SWG (bus bar testing – Relay acceptance & final setting
(P3U30) – MCCB – CT & VT – Functional test)