ICEG ARABIA Preloader
TRANSMISSION I DISTRIBUTION I SUBSTATION I RENEWABLES

New Capital ministries Counsil B , EGYPT

Aug 21, 2025 3 mins read

The New Capital Ministries Council B project in Egypt was executed by Igec, and the client was Orascom Construction, with Dar al Handasah as the consultant.

The scope of the project included the pre-commissioning and commissioning of the electrical system, which consisted of several components such as ABB Main Distribution Board, ABB SMDB, ABB ESMDB, ABB Power Factor Correction Panel, and ABB Generator Panel. The goal of the project was to ensure that the electrical system was properly installed, tested, and commissioned before the buildings were occupied. Igec’s team of experienced engineers and technicians were responsible for the successful execution of the project, and ensured that all work was carried out to the highest standards of quality and safety. 

eree

Project Facts and Figures

End UserDar al handasah
Main contractorOrascom construction

Pre- Commissioning and commissioning the electrical system including but not limited to,

  • ABB Main Distribution Board.
  • ABB SMDB.
  • ABB ESMDB.
  • ABB Power Factor Correction Panel. ABB Generator Panel.