End User: SEC 
Contractor: CEPCO 
Status: Completed
- Replacement exist line distance relay by GE Micom P543.
- Isolation and replacement.
- SWGR scheme check.
- CT, VT, CB testing.
- Cable line parameter testing.
- Secondary loop test.
- Primary loop test. 
- SPL review with open/closed loop test.
- End to End test.
- Final trip test