The 500/220/66/11 kV Kafr El Sheikh Substation is a high voltage electrical substation located in Kafr El Sheikh, Egypt.
The substation is developed by the Egyptian Electricity Transmission Company (EETC) and it is intended to reinforce the existing electrical grid and to improve the power supply in the region. The project will include the construction of a 500/220/66/11 kV substation, as well as the installation of transformers and other equipment necessary for the transmission and distribution of electricity. The substation will also include infrastructure and utilities, such as power and water supply, storage and transportation facilities. The project is expected to improve the reliability and efficiency of the power supply in the region, and to support the government’s efforts to address the increasing demand for electricity in the country.
Project Facts and Figures
End User | EETC |
Main contractor | ZTPC |
Testing and Commissioning 500kV/220kV/66kV/11kV substation electrical equipment including but not limited to,