Additional Installation Testing And Commissioning Work of Gamsa 220/66/22kV GIS

May 03, 2025 1 mins read

Installation and Testing new 220/66kV Line protection Panels





 

WhatsApp-Image-2023-04-10-at-3.2

 

Project Facts and Figures

End UserEETC
Main contractorSieyuan ELECTRIC CO

Installation and Testing new 220/66kV Line protection Panels

  • - demolishing the old panels
  • - installation new panel .
  • - Line protections Relay (NR) testing and final setting implementation
  • - End to End test
  • - Line enegization