End User: SEC Contractor: CEPCO Status: Ongoing
- 115KV Testing and Commissioning Activities for Protection panels at
TUWAIQ.
- 115KV Testing and Commissioning for Protection panels at RIC substation.
- Open loop testing and commissioning.
- Closed loop testing and commissioning.